The Claim Window 2026: Three Clocks That Start When Your Tile Container Arrives

The container is discharged on a Tuesday, devanned on Wednesday, and on Thursday someone notices a third of the pallets are a shade off. By then three clocks are already running against three different parties, and none of them started when you noticed. They started when the goods were handed over.

L&Q GLOBAL is a building-materials procurement office in Foshan, China, working with importers and distributors on factory selection, independent QC and consolidated loading. This is the part of the job that begins after the vessel sails, where most importers learn too late that a claim is not an argument. It is a file.

1. The container is inspected twice, and only one inspection is evidence

Every serious tile order gets a pre-shipment inspection. An inspector samples each production lot and judges it against an agreed acceptance quality limit, using the sample sizes and switching rules of ISO 2859-1, the AQL standard now in its third edition (January 2026). It answers one question precisely: did this lot conform when it was packed?

It cannot answer Thursday's question: are these the goods that were packed, and did they survive the voyage? A sample drawn in Foshan says nothing about container sweat in week three, a dropped pallet at transhipment, or a pallet count that was wrong at loading. The two are halves of one chain.

2. Clock one: the seller, and a deadline with no number on it

Where buyer and seller sit in different Contracting States, international sales are governed by default by the UN Convention on Contracts for the International Sale of Goods. China has been a Contracting State since 1 January 1988, and the Convention applies directly to a China-to-overseas sale unless the contract excludes it.

Article 38 requires the buyer to examine the goods within as short a period as is practicable, and expressly allows examination to be deferred until after arrival where the contract involves carriage. That is the legal basis for inspecting at your warehouse rather than the factory gate.

Article 39 is the one that ends claims. The buyer loses the right to rely on a lack of conformity if notice specifying its nature is not given within a reasonable time after discovery. The outer limit is two years from the date the goods were actually handed over, unless a contractual guarantee period is inconsistent with it. Article 40 closes the door the other way: a seller who knew, or could not have been unaware, and said nothing, cannot rely on either article.

The practical sting: the Convention never defines reasonable time in days. For tiles it collapses fast, because tile evidence is destroyed by use. Once cartons are opened and pallets broken for installation, you can no longer show that a warped edge or a shade shift arrived with the goods rather than appearing in your own store. A claim strong in week one is arguable in week six and worthless in month six, not because two years expired but because the evidence did.

Under Article 36(1) the seller is liable for a lack of conformity that existed when risk passed, even if it appears later. The principle is easy; proving which side of the ship it happened on is not.

3. Clock two: the carrier, one year, and a very short memory

Claims against the shipping line run on a different statute. Under Article III rule 6 of the Hague-Visby Rules, mirrored for China in Article 257 of the Maritime Code, the carrier is discharged from all liability unless suit is brought within one year of delivery, or of the date delivery should have taken place.

One year sounds generous. It is not: the duty of care runs from loading to discharge, while the time bar runs wider than the duty. And a container delivered with the seal intact and the doors undamaged gives the carrier a strong position, because breakage inside an unopened box is more often stowage or packing failure than a casualty at sea.

Incoterms sharpen it. Under Incoterms 2020, FOB and CIF pass the risk of loss or damage when the goods are on board at the port of shipment. After that the goods are at your risk, which is why the insurance clock exists and why "the factory should pay" is the wrong first sentence in a transit case.

4. Clock three: the insurer, and sixty days that do not wait for your warehouse

Cargo cover is described as warehouse to warehouse, which sounds like it follows the goods to your door. The wording is narrower. Under Clause 8 of the Institute Cargo Clauses 2009, cover terminates on whichever of four events occurs first, and one is the expiry of 60 days after completion of discharge from the overseas vessel at the final port of discharge. Delivery to your final warehouse, or storage at an intermediate one, ends it earlier.

Two consequences surprise buyers. A port delay, a customs query or a slow haulier can consume the cover before the goods reach you, because the clock runs from discharge. And on CIF the seller need only arrange minimum cover, Clause (C), which insures a named list of perils rather than all risks, so the policy may not respond to the loss you actually suffered.

5. The three clocks, side by side

ClockAgainst whomRuns fromWhat ends it
Notice of non-conformityThe sellerDiscovery, or when you ought to have discovered itReasonable time, with no fixed number; in practice the survival of your evidence
Absolute outer limitThe sellerDate the goods were actually handed overTwo years, unless a contractual guarantee period is inconsistent with it
Carrier liabilityThe shipping lineDelivery, or the date delivery should have taken placeOne year, and only if suit is brought
Cargo insuranceThe insurerCompletion of discharge at the final port60 days, or earlier delivery or storage election

6. Six failures, six different defendants

Most claim files fail at step one: naming the wrong party.

What you seeMost likely causeWho it belongs toThe proof that decides it
Shade shift between pallets, size drift, warpage, lippageProduction variation across lots or linesSeller, as a conformity issueSamples retained per pallet, compared under one light source, plus the approved reference sample
Corners crushed, cartons torn, breakage on outer rowsHandling or stowageCarrier or insurerPhotos before devanning, seal number, container interior condition, survey report
Pallet count or square metres shortLoading short, or pilferageSeller if the seal was intact; carrier if notTally against the packing list, seal record on the bill of lading, joint survey
Wet cartons, white bloom, mould on packagingContainer sweat or water ingressUsually the insurer; carrier only if the box was not watertightContainer inspection photos, surveyor finding on the ingress point
Wrong size, finish or shade nameLoading error at the factorySellerCarton labels against the order confirmation and approved sample
Breakage with intact packaging and no external marksPacking specification too weak for the routeThe party that specified packing, normally the sellerThe agreed packing specification, and whether the delivered packing matched it

Damaged tiles is not a claim. It is a symptom with six possible causes, and the cause selects the defendant, the clock and the evidence.

7. The first 72 hours

  1. Photograph the seal before you cut it, container number in the same frame. If the seal is broken or mismatched, stop and call the carrier before opening.
  2. Note exceptions on the delivery receipt. Received subject to survey costs nothing and preserves the carrier claim. A clean signature does the opposite.
  3. Tally by pallet and carton against the packing list before anything moves to the racking. Counts taken after distribution are opinions.
  4. Photograph the container interior: floor, walls, ceiling, position of damaged pallets. Water marks overhead tell a different story from random breakage.
  5. Keep suspect pallets wrapped until a surveyor sees them. Devanning destroys the only layout evidence you will ever have.
  6. Retain physical samples: three tiles per affected pallet, labelled, plus a control tile. Shade arguments are won with tiles on a table, not photographs.
  7. Send written notice stating the nature of the non-conformity, and invite the seller to examine the goods or send an agent. That is what Article 39 contemplates; a complaint that there is a problem is not a notice.
  8. Notify insurer and carrier the same week. Parallel tracks, not fallbacks: waiting for the seller can consume the 60-day cover.

8. What you can recover, and what you cannot

The Convention's remedies for non-conforming delivery are replacement or repair, price reduction, and damages for loss foreseeably suffered. In tile practice four outcomes cover almost every file: replacement of the affected quantity on the next run; a credit note against the next order, usually cheapest because nobody pays freight twice; re-sorting and grading at your warehouse with the seller paying the labour; and a price reduction for a small shortfall.

What rarely survives is the claim for everything downstream: lost margin, project penalties, a delayed opening. Recoverable in principle, hard in practice, because you must prove the loss was foreseeable at contracting and caused by the shortfall. Most importers do better converting a strong file into a credit note and a better packing spec.

One habit separates a credit note from an argument: settle in writing, with a debit note number. A promise to fix it on the next order is not a settlement. It is a hope with a date on it.

9. The four mistakes that end claims

Installing first, claiming later. Once the material is fixed you cannot show what arrived, and the defect becomes opinion.

Signing a clean delivery receipt. It does not end a seller claim, but it nearly ends a carrier claim: the defence writes itself.

Claiming against the wrong party. Incoterms moves risk, not the quality obligation. Transit damage after loading is your risk; a production defect that existed at loading stays with the seller under Article 36(1), however late it surfaces.

Treating the 60 days as a formality. That is the clock that expires while everyone is still being reasonable with each other.

10. Clauses worth fixing before the next container

Almost every claim problem is cheaper in the contract than in the dispute.

ClauseWeak defaultWhat to write instead
ExaminationSilent, so the practicable-period test appliesAt buyer warehouse within 14 days of arrival, by a named surveyor
NoticeReasonable timeWritten notice within 7 days of discovery, samples retained 90 days
Shade toleranceSilent, so every shade shift becomes a disputeReference sample approved in writing, stated acceptable variation, lot marking
PackingExport packingPallet type, corner protection, stretch and strapping spec, maximum stack height
InsuranceCIF with Clause (C) by defaultClause (A), 110% of CIF value, with the 60-day limit noted
RemedySilent, so every claim is negotiated from scratchCredit note for verified shortfalls; replacement for conformity failures
Governing lawUnclear whether the Convention appliesState it expressly: the Convention applies, or name the law and exclude it

11. Where a procurement office changes the arithmetic

A claim is decided by what you can prove, and what you can prove is decided before the container sails. Inspection is booked against a defined AQL rather than a look-over, the approved reference sample is retained on both sides so a shade argument has a baseline, and loading is photographed pallet by pallet with the seal number recorded. When the container arrives, the arrival file already has something to compare against: the difference between the tiles look different and a documented non-conformity.

Our six-step sourcing process ends with the shipment, not the invoice, and the same discipline carries into mixed containers. If you are filing now and the file is thin, the next container is where the fix belongs. See what a pre-shipment inspection should cover, and the pre-sail half of this story in why a container is judged before it sails.

None of this makes a bad batch good. It makes the bad batch provable, in the only window where proving it still pays.

FAQ

How long do I have to claim for defective tiles?

Notice within a reasonable time of discovery, and in any event within two years of handover, where the UN Sales Convention applies. The practical deadline is far earlier: your evidence dies when the goods are installed.

Does a pre-shipment inspection protect me after arrival?

Only as a baseline. It proves the lot conformed when packed; it cannot prove the arriving goods are the packed goods, and it says nothing about five to seven weeks at sea.

What if I already signed without noting damage?

The seller claim survives; the carrier claim is badly weakened. Photograph everything now, keep the pallets intact, commission a survey, and notify the insurer inside 60 days.

Who pays for the surveyor?

Whoever commissions it, in the first instance. Where non-conformity is established, the cost is part of the loss and belongs in the claim.

Is a credit note better than a replacement shipment?

Usually yes for a partial shortfall: nobody pays ocean freight twice. Replacement makes more sense when a whole run is affected and the material is still needed.

If a container has arrived wrong and the file is still thin, send the packing list, the delivery receipt, the photos you have and the date of discharge. We will tell you which clock is closest to running out, and what to do this week rather than next month.

About the author: JOY YING is the Founder of L&Q GLOBAL, a building-materials procurement office based in Foshan, China, with 19 years of foreign-trade experience inside a top-tier China tile manufacturer. L&Q helps importers, distributors and contractors source verified factories, run independent QC before shipment and consolidate mixed containers from China.

✉ joyying1105@gmail.com — questions about this guide, or about a specific arriving container, are welcome.

Sources

UNCITRAL, CISG text and status (Arts. 36, 38, 39, 40); Incoterms 2020 FOB / CIF, as endorsed by UNCITRAL; Maritime Code of the PRC, Art. 257; UCP 600, Art. 14(b); ISO 2859-1:2026. Clause 8 wording follows the standard Institute Cargo Clauses 2009 text; check your own policy. Commercial practice, not legal advice.